Eliminate build-up on the preheating tower
21 November 2022
Agglomeration on the walls
21 November 2022Cement plant in Turkey
PROBLEM:
Build-ups in the riser ducts leading to production stops.
PRODUCT:
Raw Meal (future clinker and then cement)
OBJECTIVE:
To remove the concretions that disrupt the industrial process and reduce the production capacity.

SOLUTION:
Installation of 4 MACSYS Wireless: 2 MACSYS Wireless with 8 heads DN100 + 2 MACSYS Wireless with 5 heads DN100
RESULT:
No more kiln shutdowns related to blockage of the riser ducts